2.3.Manufactured Capital

Interview with Vice President for Capital ConstructionRead

2.3.1. Construction Phase Management

in the provinceof Jiangsu,Lianyungang city

Tianwan NPP (China)

Customer — Jiangsu Nuclear Power Corporation (JNPC).
Reactor type VVER-1000
I stage (Units 1, 2)
2 х 1000 MW
were put into commercial operation in 2007.
II stage (Units 3, 4)
2 х 1000 MW
were put into commercial operation in 2018.
IV stage (Units 7, 8)
2 х 1200 MW
General Contract for the construction of Units 7, 8 was signed in March 2019.

2018 Key Results

  • Putting Unit 3 into commercial operation;
  • Physical start-up of Unit 4;
  • Putting Unit 4 into commercial operation.

Plans for 2019

  • Ensuring conditions for provisional acceptance of Unit 4 within our area of responsibility.
in southern India,in Tamil Nadu state

Kudankulam NPP (India)

Customer — Nuclear Power Corporation of India Ltd. (NPCIL).
Reactor type VVER-1000
Construction
on the terms of
the EP-Contract
The Multi-D
digital platform

is used
I stage (Units 1, 2)
2 х 1000 MW
were connected to the grid,
Unit 1 is accepted by the Customer,
Unit 2 is put into the warranty operation.
II stage (Units 3, 4)
2 х 1000 MW
III stage (Units 5, 6)
2 х 1000 MW

2018 Key Results

  • Release of the detailed design documentation is provided for commencement of earthworks and excavation of pits for main buildings of Unit 5;
  • Shipment of the equipment to the Customer is performed, which consists of five shipload lots, with the total volume of 32 300 m3, including the long manufacturing cycle equipment: installation of the molten corium trap, reactor, turbine, turbine-generator and four steam generators for Unit 3, as well as turbine generator for Unit 4.

Plans for 2019

  • Works on implementation of the main contracts signed with the Customer;
  • Fulfillment of contractual obligations in terms of manufacturing and supply of the long manufacturing cycle equipment and other equipment for Units 3 and 4;
  • Fulfillment of contracting schedule on the long manufacturing cycle equipment for Units 5 and 6.
near Dhaka city

Rooppur NPP (Bangladesh)

Customer — Bangladesh Atomic Energy Commission (BAEC).
Reactor type VVER-1200 Safety generation III+
Construction
on the terms of
the EPC-Contract
The Multi-D
digital platform

is used
The project
implements Rosatom
Production System
I stage (Units 1, 2)
2 х 1150 MW

2018 Key Results

  • Starting of the foundation slab reinforcing for Unit 1 turbine building;
  • Obtaining the construction license for Unit 2;
  • Commencement of works on the foundation slab concreting for Unit 1 turbine building;
  • Starting of the foundation slab concreting for Unit 2 reactor building;
  • Shipment of the air-lock (standby) for the personnel of Unit 1 to the Customer.

Plans for 2019

  • Construction and erection works at Units 1 and 2 according to the construction schedule.
near Mersin city

Akkuyu NPP (Turkey)

Customer — AKKUYU NÜKLEER ANONİM ŞİRKETİ.
Reactor type VVER-1200 Safety generation III+
The Multi-D
digital platform

is used
The project
implements Rosatom
Production System
I stage (Units 1, 2, 3, 4)
4 х 1200 MW

The project of Akkuyu NPP is a generic project of a new-generation nuclear power plant with improved technical and economical parameters, up-to-date safety and reliability indicators and optimization of capital investment in the NPP construction.

Akkuyu NPP contributes significantly to the improvement of local, regional and national economics both during the NPP construction and operation.

During the construction, the project provides for large-scale involvement of local companies in the NPP construction, provision of manpower, construction materials and equipment and other services rendering.

Apart from workplaces created during the NPP construction, additional services will develop, such as stores, banks, hospitals, etc. This all will create additional opportunities for employment.

2018 Key Results

  • The license of Turkish Atomic Energy Authority (TAEK) for construction of Unit 1 was obtained;
  • “First concrete” pouring in the foundation slab of Unit 1 reactor building was implemented;
  • The limited license of Turkish Atomic Energy Authority (TAEK) for construction of Unit 2 was obtained;
  • Manufacturing of Unit 1 reactor pressure vessel commenced.

Plans for 2019

  • Completion of foundation slab concreting for Unit 1 reactor building;
  • Ensuring performance of design and survey works, construction and erection works according to the Integrated Schedule of Akkuyu NPP Construction Project (Units 1, 2, 3, 4) within the area of JSC ASE responsibility.
in the region of Matruh,in the vicinity ofEl-Dabaa city

El-Dabaa NPP (Egypt)

Customer — Nuclear Power Plants Authority of the Arab Republic of Egypt.
Reactor type VVER-1200 Safety generation III+
60 years NPP design lifetime
Construction
on the terms of
the EPC-Contract
The Multi-D
digital platform

is used
The project
implements Rosatom
Production System
I stage (Units 1, 2, 3, 4)
4 х 1194 MW

Russian-Egyptian cooperation in the nuclear field has a history of 50+ years. In 1961, the first research reactor in Egypt was built on the basis of Soviet technologies. It marked the beginning of Egypt’s long way in nuclear technologies mastering. Construction project of the first Egyptian El-Dabaa NPP is intended to become a new page in our countries’ cooperation and a driver of Russian-Egyptian relations.

The NPP construction will have a positive impact on the industrial development of Matruh region and the entire Egypt and will have a significant effect on the country’s GDP. The positive result will be achieved both due to the direct influence of the project — proceeds of local subcontractors and indirect impact of multiplying effect: growth of “allied industries” orders (suppliers of materials, construction machines, providers of utilities and other services to direct project contractors (“indirect effect”); growth of the population’s purchasing power and, consequently, growth of orders for industries servicing the consumer demand (“induced effect”). Besides, additional workplaces will be created in construction and machine-building industries in the course of project implementation.

2018 Key Results

  • Completion of the 4th stage of the engineering survey on the construction site and in the Mediterranean Sea waters adjacent to it;
  • Preparation of the documents for obtaining of the license for construction of Units 1, 2 (PSA, PSAR and parts of the Basic Design);
  • Preparation of the first-priority detailed design documentation on construction and erection works of the preparatory period.

Plans for 2019

  • Continued elaboration and review of El-Dabaa NPP basic design;
  • Preparation for commencement of construction and erection works on the construction site.
Reference NPP
Leningrad NPP-2 constructed in Russia in accordance with AES-2006E design.
Its Unit 1 was accepted for commercial operation in 2018.
province of North Ostrobothnia,Pyhäjoki municipality

Hanhikivi-1 NPP (Finland)

Customer — Fennovoima Oy (Owner).
General Contractor — RAOS Project Oy.
General Designer — JSC ATOMPROEKT.
Reactor type VVER-1200 Safety generation III+
The Engineering Division is commissioned
to develop the design documentation and detailed
design documentation of Nuclear Island
buildings and structures.
The Multi-D
digital platform

is used
I stage (Unit 1)
1 х 1265 MW

2018 Key Results

  • Development of design and licensing documentation and its consistent agreement with the Owner (Fennovoima Oy) are continued;
  • Highly detailed 3D-model of the NPP was developed.

Plans for 2019

  • Continued works of the preparatory stage.
near Paks town

Paks II NPP (Hungary)

Customer — MVM Paks II (since 06.11.2017, known as Paks II Nuclear Power Plant Private Company Limited by Shares).
Reactor type VVER-1200 Safety generation III+
Construction
on the terms of
the EPC-Contract
The Multi-D
digital platform

is used
The project
implements Rosatom
Production System
I stage (Units 1, 2)
2 х 1198 MW

2018 Key Results

  • Signing of the Supplement to the EPC Contract allowing to commence the CEB construction;
  • A part of Site 1 has been received from the Hungarian Party for construction of the first stage of the Construction and Erection Base buildings;
  • Signing of the contract for manufacturing and supply of the package of the automated process control system;
  • Nuclear evaluation of the turbine hall equipment supplier;
  • Tendering procedures for the Construction and Erection Base buildings have been organized;
  • Conclusion of the contract for manufacturing and supply of the nuclear steam generating plant;
  • Audit of the nuclear qualification of JSC Atomenergomash, nuclear steam generating plant supplier.

Plans for 2019

  • Generation of documentation for Application for project implementation license;
  • Start of construction of the first administrative and amenity building of the Construction and Erection Base.
near Ostrovets town

Belarus NPP

Customer — Belarus Nuclear Power Plant RUE.
Reactor type VVER-1200 Safety generation III+
Construction
on the terms of
the EPC-Contract
The Multi-D
digital platform

is used
The project
implements Rosatom
Production System
I stage (Units 1, 2)
2 х 1150 MW

Construction of Belarus NPP is the largest infrastructure project which provided about 2400 workplaces, both at the NPP and in the servicing companies. Currently, over 30 local companies are involved in the NPP construction.

Diversification of urban community economics provides for siting of new high-tech enterprises producing radio, TV and communication instruments, machines and equipment for public and consumer services. As a result, occupation in technological industries will increase nearly 11-fold.

2018 Key Results

  • Works on welding of the main coolant pipeline of Unit 2 were completed;
  • Works on the reactor assembly of Unit 1 were commenced;
  • Putting of GIS-330 kV into operation;
  • The activities within the framework of “Green Square” Project were implemented.

Plans for 2019

Unit 1:

  • First connection of the Unit to the grid.

Unit 2:

  • Auxiliary power supply through a design circuit;
  • Start of safety systems flushing to an open reactor.
near Volgodonsk city

Rostov NPP

Customer — JSC “Rosenergoatom”.
Reactor type VVER-1000
Construction
on the terms of
the EPC-Contract
The Multi-D
digital platform

is used
The project
implements Rosatom
Production System
I stage (Units 1, 2, 3, 4)
4 х 1000 MW

For the construction of Unit 4, 40+ construction and erection companies with over 3.3 thousand people on their staff list were involved and more than 1400 workers took part in core operations. Within the construction period, over 200 representatives of student brigades actively participated in the construction of Rostov NPP.

2018 Key Results

  • Power start-up of Unit 4 of Rostov NPP;
  • Commissioning of Unit 4 of Rostov NPP.

Plans for 2019

  • Securing guarantee obligations to eliminate non-conformances revealed during the guarantee period.
near settlement Makarovka,Kurchatov district,Kursk region

Kursk NPP-2

Customer — JSC “Rosenergoatom”.
Reactor type VVER-TOI
Construction on the terms of
the general contractor contract
for Kursk NPP-2 construction
The Multi-D
digital platform

is used
The project
implements Rosatom
Production System
I stage (Units 1, 2)
4 х 1255 MW

Kursk NPP-2 is being constructed in order to replace the decommissioned units of the operating Kursk NPP with RBMK-1000 reactors. Commissioning of the first two units of Kursk NPP-2 is planned to be synchronized with the decommissioning of Units 1 and 2 of the operating plant.

Additional tax deductions from implementation of Kursk NPP-2 construction project come to the regional budget.

Besides, over 5 thousand people will be involved in the construction of Kursk NPP-2 in the nearest years. Their presence will give development to associated supplementary business of services which will be provided by local enterprises and companies.

2018 Key Results

  • Start of the foundation slab concreting for Unit 1 reactor building;
  • Start of the foundation slab concreting for Unit 1 turbine building;
  • Start of the foundation slab reinforcing for Unit 2 reactor building;
  • The molten corium trap (”core catcher”) was installed in the designed position at Unit 1.

Plans for 2019

  • Installation of the molten corium trap at Unit 1 has been completed;
  • Completion of the foundation slab concreting for the unit reactor building;
  • Start of the installation of the molten corium trap body at Unit 2.
near Novovoronezh town

Novovoronezh NPP-2

Customer — JSC “Rosenergoatom”.
Reactor type VVER-1200 Safety generation III+
Construction
on the terms of
the EPC-Contract
The Multi-D
digital platform

is used
The project
implements Rosatom
Production System
I stage (Units 1, 2)
2 х 1200 (1198) MW

Totally in 2018, 40 contractor companies were involved in the construction of Novovoronezh NPP-2, including 12 companies registered in the area of Novovoronezh town and Voronezh region. Average annual number of the main construction and erection personnel from our own resources and contractor companies, involved in the construction, amounts to 3000 people.

Considering revenue from contractor companies and subcontractors involved in the erection of the new unit, the local structure of JSC “Rosenergoatom” is the leader in payments into the consolidated budget of Voronezh region.

2018 Key Results

  • Commencement of the stage of cold and hot functional tests of the reactor plant at Unit 2.
  • Completion of cold and hot functional tests of the reactor plant at Unit 2.
  • Revision of the reactor plant main equipment began.

Plans for 2019

  • Start of the physical start-up of Unit 2.
  • Start of the power start-up of Unit 2.
  • Completion of Unit 2 trial and commercial operation.
  • Obtaining the commissioning permit for Unit 2.